Official Exam Paper TranscriptB.Tech. 5th Semester Examination, 2023
Bihar Engineering University, Patna
B.Tech. 5th Semester Examination, 2023

Hydrology & Water Resources Engineering

Time: 03 HoursCode: 101505Full Marks: 70

Instructions:

  1. The marks are indicated in the right-hand margin.
  2. There are NINE questions in this paper.
  3. Attempt FIVE questions in all.
  4. Question No. 1 is compulsory.
Q.1 Answer any seven of the following:[14]
  1. Precipitation that falls near the equator is most likely to fall with time is known as

    1. Snow on the ocean
    2. Rain on to land
    3. Snow on to glacier
    4. Rain on to the road
  2. The term base flow denotes

    1. Delayed groundwater flow reaching a stream
    2. Delayed groundwater and snowmelt reaching a stream
    3. Delayed groundwater and interflow
    4. The annual minimum flow in a stream
  3. The total rainfall in a catchment of area 1200 km2 during 6-h storm is 16 cm and surface runoff due to the storm is 1.2×105 m3. The φ-index is

    1. 1 cm/h
    2. 2 cm/h
    3. 0 cm/h
    4. Can't be estimated with the given data
  4. A 90 km2 catchment has the 4-h unit hydrograph which can be approximated as a triangle. If the peak ordinate of this hydrograph is 10 m3/s the time base is

    1. 120 h
    2. 50 h
    3. 100 h
    4. None of these
  5. The geologic formation which is neither porous nor permeable and hence no yield of ground water is termed as

    1. aquiclude
    2. aquifer
    3. aquitard
    4. aquifuge
  6. The Probability of a 10-year flood to occur at least once in 6 years is

    1. 35%
    2. 53%
    3. 41%
    4. 60%
  7. Darcy's law is valid in a porous media flow if the Reynolds number is less than unity, this Reynold number is defined as

    1. (discharge velocity * maximum grain size) / ν
    2. (discharge velocity * average grain size) / ν
    3. (discharge velocity * pore size) / ν
    4. (actual velocity * average grain size) / ν
  8. How that area will be irrigated with if looping is there in ridge line?

    1. Side slope canal
    2. Contour canal
    3. Watershed canal
    4. Field channel
  9. Kor-watering is the irrigation water supplied to a crop

    1. at the time of its sowing
    2. just before harvesting
    3. about three weeks after sowing
    4. about three weeks before harvesting
  10. The instrument to measure wind velocity is

    1. current meter
    2. atmometer
    3. aerometer
    4. anemometer
Q.2 Solve both questions:[14]
  1. Explain various methods of obtaining mean precipitation with equations.

  2. The normal annual rainfall of stations A, B, C and D in a catchment are 809.7, 675.9, 762.8, 920.1 mm respectively. In the year 2023, the station D was inoperative while stations A, B, C recorded annual rainfall of 911.1, 722.3, 798.9 mm respectively. Use normal ratio method to estimate the missing rainfall data at D in the year 2023.

Q.3 Solve both questions:[14]
  1. Discuss various factors affecting evaporation. What are the possible sources of error in the measurement of the rainfall.

  2. The following meteorological data pertain to a large reservoir with water spread area 15 km2. The data represents the average values for the day. Water temperature = 24\circ C, Air Temperature = 26\circ C, Atmospheric pressure 752 mm of mercury, wind speed at 0.5 m above G.L = 25.3 km/h, relative humidity r = 46%. Estimate average daily evaporation from the reservoir and evaporation loss from the reservoir for a period of one week using Meyer's and Rohwer's equations.

Q.4 Solve both questions:[14]
  1. What is runoff? Explain with sketch different types of catchments.

  2. Explain the rainfall-runoff relationship using regression analysis (any one method).

Q.5 Solve both questions:[14]
  1. Define "unit hydrograph". What are the assumptions, uses and limitations of hydrograph theory?

  2. A 6h storm produced rainfall intensity of 7, 18, 25, 12, 10 and 3 mm/h in successive one hour interval over a basin of 800 sq.km. The resulting runoff is observed to be 2640 hectare-metres. Determine the φ-index for the basin.

Q.6 Solve both questions:[14]
  1. Explain with equations of various types of irrigation efficiencies.

  2. The gross commanded area for an irrigation canal is 20,000 hectares out of which 75% is culturable CA. Intensity of irrigation is 40% for rabi and 10% for rice. If Kor period is 4 weeks for rabi and 2.5 weeks for rice, determine outlet discharge. Outlet factors for rabi and rice may be taken as 1800 ha/cumec and 775 ha/cumec respectively. Also calculate delta for each case.

Q.7 Solve both questions:[14]
  1. What is canal? List its type and explain with neat sketch its classification based on alignment.

  2. Explain different storage zones of reservoir with neat sketch.

Q.8 Solve both questions:[14]
  1. Define the following: (i) Paleo Irrigation (ii) Kor Watering (iii) intensity of irrigation (iv) Time factor (v) capacity factor (vi) crop rotation.

  2. Design an irrigation channel in alluvial soil according to Lacy's silt theory for the following data: Full Supply discharge = 10 cumecs, Lacy's Silt Factor = 0.9, side slope of channel = 1/2(H) : 1(V). Also determine bed slope of the channel.

Q.9 Solve both questions:[14]
  1. Explain (i) Investigation for reservoir site (ii) Economic Height of Dam.

  2. What are flow irrigation and lift irrigations? Explain types of flow irrigation.

Related Official Syllabus

Professional Practice, Law & Ethics

101505

Official BEU curriculum units & topics for this examination subject.

Unit 1.0: Professional Practice

Respective roles of various stakeholders: Government (constituting regulatory bodies and standardization organizations, prescribing norms to ensure safety of the citizens); • Standardization Bodies (ex. • BIS, IRC)(formulating standards of practice); professional bodies (ex. • Institution of Engineers(India), Indian Roads Congress, IIA/ COA, ECI, Local Bodies/ Planning Authorities) (certifying professionals and offering platforms for interaction); • Clients/ owners (role governed by contracts); • Developers (role governed by regulations such as RERA); • Consultants (role governed by bodies such as CEAI); • Contractors (role governed by contracts and regulatory Acts and Standards); • Manufacturers/ Vendors/ Service agencies (role governed by contracts and regulatory Acts and Standards)

Unit 2.0: Professional Ethics

Definition of Ethics, Professional Ethics, Business Ethics, Corporate Ethics, Engineering Ethics, Personal Ethics; • Code of Ethics as defined in the website of Institution of Engineers (India); • Profession, Professionalism, Professional Responsibility, Professional Ethics; • Conflict of Interest, Gift Vs Bribery, Environmental breaches, Negligence, Deficiencies in state-of-the-art; • Vigil Mechanism, Whistleblowing, protected disclosures.

Unit 3.0: General Principles of Contracts Management

Indian Contract Act, 1972 and amendments covering General principles of contracting; • Contract Formation & Law; • Privacy of contract; • Various types of contract and their features; • Valid & Voidable Contracts; • Prime and sub- contracts; • Joint Ventures & Consortium; • Complex contract terminology; • Tenders, Request For Proposals, Bids & Proposals; • Bid Evaluation; • Contract Conditions & Specifications; • Critical /“Red Flag” conditions; • Contract award & Notice To Proceed; • Variations & Changes in Contracts; • Differing site conditions; • Cost escalation; • Delays, Suspensions & Terminations; • Time extensions & Force Majeure; • Delay Analysis; • Liquidated damages & Penalties; • Insurance & Taxation; • Performance and Excusable Non-performance; • Contract documentation; • Contract Notices; • Wrong practices in contracting (Bid shopping, Bid fixing, Cartels); • Reverse auction; • Case Studies; • Build-Own-Operate & variations; • Public- Private Partnerships; • International Commercial Terms;

Unit 4.0: Arbitration, Conciliation and ADR (Alternative Dispute Resolution) System

Arbitration – meaning, scope and types – distinction between laws of 1940 and 1996; • UNCITRAL model law – Arbitration and expert determination; • Extent of judicial intervention; • International interim measures by court; • Arbitration tribunal – appointment, challenge, jurisdiction of arbitral tribunal, powers, grounds of challenge, procedure and court assistance; • Award including Form and content, Grounds for setting aside an award, Enforcement, Appeal and Revision; • Enforcement of foreign awards – New York and Geneva Convention Awards; • Distinction between conciliation, negotiation, mediation and arbitration, confidentiality, resort to judicial proceedings, costs; • Dispute Resolution Boards; • Lok Adalats

Unit 5.0: Engagement of Labour and Labour & Other Construction-related Laws

Role of Labour in Civil Engineering; • Methods of engaging labour- on rolls, labour sub-contract, piece rate work; • Industrial Disputes Act, 1947; • Collective bargaining; • Industrial Employment ( Standing Orders) Act, 1946; • Workmen’s Compensation Act, 1923; • Building & Other Construction Workers (regulation of employment and conditions of service) Act (1996) and Rules (1998); • RERA Act 2017, NBC 2017.

View Complete 5th Semester Syllabus

Prepare Better with BEU Connect

  • Download papers for 100% offline study
  • Ask AI for step-by-step problem breakdown
  • Attempt official GATE CBT mock tests
  • Calculate SGPA and track attendance
Download Android App